COVID–19 NEWS   S Korea’s new COVID-19 cases bounce back to over 10,000 amid resurgence woes | Italy's COVID-19 transmission rate rises for 4th consecutive week | N Korea's first COVID-19 cases traced to area bordering S Korea: State media | COVID: Rise in new infections, drop in death cases last week - Health DG | South Korea’s COVID-19 vaccine candidate inches closer to launch after experts' approval Recommendation | 
BUSINESS

CEO: TRX infrastructure 99 pct completed

21/05/2022 09:57 AM

KUALA LUMPUR, May 20 (Bernama) -- Tun Razak Exchange’s (TRX) infrastructure is now 99 per cent completed, with the remaining one per cent nearing completion, master developer of the financial district TRX City Sdn Bhd said.

“Although we were constrained by the Movement Control Order (MCO) resulting from the COVID-19 pandemic, we managed to continue developing TRX and the successfully completed buildings today are Menara Prudential and HSBC Bank,” TRX City chief executive officer Datuk Azmar Talib told the media at the Hari Raya open house at Raintree Plaza, TRX here today.

“As for the Affin Bank building, we have obtained a Certificate of Completion and Compliance (CCC) and it will be ready for occupation in the third quarter of this year," he said.

Azmar said although TRX City is the master developer, the development of the individual plots depend on the respective land owners. 

On TRX’s retail updates, Azmar said its main commercial (area) will be the Lifestyle Quarter, developed by a 60:40 joint venture (JV) company between Australia’s property and infrastructure group Lendlease and TRX City and this JV will manage it.

He said an announcement regarding the Lifestyle Quarter will be forthcoming.  

“We are seeing a lot of progress, but of course, the MCO had affected some of our physical progress. 

“We are trying to get back the momentum, especially (the) momentum to get retailers and (those who are) new to market to come to TRX,” he said.

On global inflationary pressures and rising interest rates, Azmar said the company does not rule out their impact on TRX, but (the fact remains that) it has completed most of the development work.

“We will be completing the work, but moving forward we have to be aware (of this inflationary pressures and rising rates) and we have to adjust with this.

“I and all the other parties are very concerned about this (and) we try to mitigate whatever risk there is,” he said.

The 70-acre TRX is expected to be completed in phases. Menara Prudential was the first office building to be occupied in 2019.

Indonesia’s Mulia group, developer of office skyscrapper Exchange 106, is seeking tenants. HSBC and Affin Bank headquarters will be operating from the district in 2022.

-- BERNAMA

 


Bernama is the trusted source of reliable real-time comprehensive and accurate news for both the public and media practitioners. Our news is published at www.bernama.com ; BERNAMA TV on: Astro Channel 502, unifi TV Channel 631, MYTV Channel 121 IFLIX; and Bernama Radio broadcasting locally on FM93.9 in Klang Valley, Johor (FM107.5), Kota Kinabalu (FM107.9) and Kuching (FM100.9).

Follow us on social media :
Facebook : @bernamaofficial, @bernamatv, @bernamaradio
Twitter : @bernama.com, @BernamaTV, @bernamaradio
Instagram : @bernamaofficial, @bernamatvofficial, @bernamaradioofficial
TikTok : @bernamaofficial

© 2022 BERNAMA   • Disclaimer   • Privacy Policy   • Security Policy