DBKL To Address Traffic Congestion At Critical Locations Through Road Upgrading Projects

27/04/2026 02:59 PM

KUALA LUMPUR, April 27 (Bernama) -- Kuala Lumpur City Hall (DBKL) is implementing three targeted road projects at critical locations identified based on an analysis of current traffic flows and projected vehicle growth.

Kuala Lumpur mayor Datuk Seri Fadlun Mak Ujud said all the projects focus on resolving bottleneck issues that affect the daily movement of city residents.

He said the project involves the construction of a road and tunnel from Jalan Kiara 7 to the SPRINT Highway (Penchala Link) in Segambut to address congestion on Jalan Desa Kiara and the Mont Kiara area which is at a critical level (LOS F) due to access and exit constraints as well as increased development density.

Ad Banner
Ad Banner

“To address this issue, DBKL will build an alternative route that connects Jalan Kiara 7 directly to the SPRINT Highway (E23 Penchala Link). This project involves the construction of a 562-metre new road as well as tunnel and bridge structures.

“Based on traffic simulations conducted, this project has the potential to improve the level of road service from LOS F to LOS C, thus reducing travel time and redistributing traffic flow in the area,” he said in a statement today.

Fadlun said the project would start in the fourth quarter of this year and is expected to be completed within two years.

Ad Banner

In addition, DBKL is also carrying out works to upgrade the Seputeh exit from the Pantai Baru Expressway (NPE) to the Kuala Lumpur-Seremban Expressway following congestion in the area, particularly involving traffic flows from Jalan Kuchai Maju, Jalan Desa and Salak which have directly affected peak hour travel.

He said the upgrading work involves adding one lane to three lanes and upgrade the road alignment and bridge along about 600 metres to increase capacity and smooth traffic flow.

He said the project is expected to start in the fourth quarter of this year and be completed within a year.

He said the project also involves upgrading the intersection of Jalan 7/24 and Jalan Lingkaran Tengah 2 (MRR2) in Wangsa Melawati which is expected to start this June and be completed within four months.

“The proposed upgrade involves widening the entrance and exit ramps, improving the intersection design and increasing road safety elements. DBKL is currently in the final stages of finalising the design before submitting it to the Selangor State Public Works Department for approval,” he said.

Fadlun said the three projects reflect DBKL's new approach of putting development proceeds back to the people through infrastructure investments that solve the city's real problems.

-- BERNAMA

 

 


BERNAMA provides up-to-date authentic and comprehensive news and information which are disseminated via BERNAMA Wires; www.bernama.com; BERNAMA TV on Astro 502, unifi TV 631 and MYTV 121 channels and BERNAMA Radio on FM93.9 (Klang Valley), FM107.5 (Johor Bahru), FM107.9 (Kota Kinabalu) and FM100.9 (Kuching) frequencies.

Follow us on social media :
Facebook : @bernamaofficial, @bernamatv, @bernamaradio
Twitter : @bernama.com, @BernamaTV, @bernamaradio
Instagram : @bernamaofficial, @bernamatvofficial, @bernamaradioofficial
TikTok : @bernamaofficial

© 2026 BERNAMA   • Disclaimer   • Privacy Policy   • Security Policy