KUALA LUMPUR, Dec 12 (Bernama) -- The construction of the Johor Bahru-Singapore Rapid Transit System (RTS) is progressing on schedule, with infrastructure works reaching 95 per cent completion as of last November, the Senate was told today.
Deputy Transport Minister Datuk Hasbi Habibollah said the installation of other system components, including rolling stock, signalling, power supply, distribution and telecommunications commenced early this month.
"So far, the government has spent RM2.5 million on completing the civil infrastructure for the RTS project on the Malaysian side.
"A total of RM5.2 billion has been allocated for the entire project in Malaysia," he said during the answer and question session in response to a question from Senator Datuk Halim Suleiman regarding the progress of the RTS Link project.
Hasbi said the RTS Link service is designed to accommodate up to 100,000 passengers daily, with trains running at a frequency of 3.6 minutes during peak hours.
He estimated that in its first year of operation, expected to begin on Dec 31, 2026, the RTS service would serve about 30,000 to 40,000 passengers daily.
Hasbi noted that Malaysia Rapid Transit System Sdn Bhd (MRTS) as InfraCo Malaysia, had granted early access to RTS Operations Pte Ltd (RTSO), which is the service operator at the Wadi Hana Depot, to begin installation of the trackworks.
-- BERNAMA
BERNAMA provides up-to-date authentic and comprehensive news and information which are disseminated via BERNAMA Wires; www.bernama.com; BERNAMA TV on Astro 502, unifi TV 631 and MYTV 121 channels and BERNAMA Radio on FM93.9 (Klang Valley), FM107.5 (Johor Bahru), FM107.9 (Kota Kinabalu) and FM100.9 (Kuching) frequencies.
Follow us on social media :
Facebook : @bernamaofficial, @bernamatv, @bernamaradio
Twitter : @bernama.com, @BernamaTV, @bernamaradio
Instagram : @bernamaofficial, @bernamatvofficial, @bernamaradioofficial
TikTok : @bernamaofficial